Novo Estado project begins energization tests on the transmission lines

Work on the implementation of ENGIE Brasil Energia’s Novo Estado Project (PNE), with 3,634 towers supporting 1,800 km of double circuit transmission lines in the states of Pará and Tocantins, is proceeding apace. Energization tests and simulations are now beginning and if successful, will allow the partial entry into operation of the system. It is critical for the public at large to be  alert to any changes and to observe safety measures in the vicinity of the towers.

In the first phase of the tests, the transmission line connecting the Itacaiúnas and Serra Pelada substations and transecting the municipalities of Marabá, Eldorado dos Carajás and Curionópolis, will be energized. “The Novo Estado Project is extremely important for the offtake of energy generated in the North and the Northeast and connecting the Xingu, Miracema and Itacaiúnas substations. The Serra Pelada substation will work as a hub for the Xingu substation, to which some major hydropower plants are connected”, ENGIE’s chief implementation officer, Márcio Neves pointed out. “The energization test phase is when we are able to show the quality in the project’s execution as well as the reliability and safety of the system”, the executive added.

It is important to respect the limits of the easement strip. This is the area established for ensuring safety along the entire route of the Transmission Line and within the confines of which construction, assembly, operation and subsequent line maintenance take place. In the case of this project, the easement strip is 55 meters wide for the stretch which connects the Itacaiúnas and Serra Pelada substations and 58 meters in the other segments of the line.

As to the precautions to be taken in the easement strip, Novo Estado wishes to notify that it is prohibited to touch or climb the transmission line towers, fly kites and launch balloons, practice activities which may result in burns or to remove rock or soil. Usage for cultivation and pasture as well as transiting along or across the easement strip is permitted as long as this is done in safety and respecting the distance of the energized towers. The energization tests will be conducted gradually pari passu with the progress of transmission line implementation.

ABOUT ENGIE

 
ENGIE is a major player in the energy transition, whose purpose is to accelerate the transition towards a carbon-neutral economy. With more than 90,000 employees in 30 countries, the Group covers the entire energy value chain, from production to infrastructures and sales. ENGIE combines complementary activities: renewable electricity and green gas production, flexibility assets (notably batteries), gas and electricity transmission and distribution networks, local energy infrastructures (heating and cooling networks) and the supply of energy to individuals, local authorities and businesses. Every year, ENGIE invests on average €12 billion per year to drive forward the energy transition and achieve its net-zero carbon goal by 2045.

 

Turnover in 2025: €71.9 billion. The Group is listed on the Paris and Brussels stock exchanges (ENGI) and is represented in the main financial indices (CAC 40, Euronext 100, FTSE Euro 100, MSCI Europe) and non-financial indices (DJSI World, Euronext Vigeo Eiris – Europe 120 / France 20, MSCI EMU ESG screened, MSCI EUROPE ESG Universal Select, Stoxx Europe 600 ESG-X).

 

In Brazil, ENGIE, one of the leaders in 100% renewable energy generation in the country, operates in generation, commercialization and transmission of electric power, gas transport and energy solutions. The Company has in the country an installed capacity of approximately 13 GW, originated from renewable sources and ow–greenhouse gas (GHG) emission sources, such as hydro, solar and biomass power plants, and windfarms.

 

With the acquisition of Transportadora Associada de Gás – TAG, completed in 2020, ENGIE now also owns the largest natural gas transportation network in the country, spanning 4,500 kilometers across 10 states and 191 municipalities. In addition, ENGIE offers a comprehensive portfolio of integrated solutions designed to reduce costs and emissions and improve infrastructure for companies, including compressed air, local solar self‑generation, biogas and biomass, energy consulting and management, HVAC systems and substations. In cities, ENGIE acts as a partner to make urban spaces more efficient and sustainable, providing solutions such as public lighting, electric mobility and district cooling.

 

ENGIE trades on B3, Brazil’s stock exchange, through its power generation and trading subsidiary, ENGIE Brasil Energia (EGIE3).. In addition to being part of B3’s Novo Mercado, the Company has been one of the few firms continuously included in the Corporate Sustainability Index (ISE) since its inception in 2005. In 2021, ENGIE Brasil Energia was also included in the Carbon Efficient Index (ICO2), which comprises shares of companies in the IBrX 100 with greater transparency in reporting GHG emissions and in preparing for a low‑carbon economy. The Company has also the certification Great Place to Work, a recognition which validates the continuous commitment to fostering a positive and inclusive work environment for all.